Weather and unforeseen conditions can/will change the schedule.
-Mowing of bunker surrounds
-Mowing of secondary rough
-Groom and dust greens on Tuesday
-Grooming of fairways on Monday/Tuesday
-Opening of practice fairway bunker at range
Monday, May 25, 2015
Wednesday, May 20, 2015
Practice Fairway Bunker Completion
On Monday we were able to complete construction of the practice fairway bunker. We are very pleased with the end result.
Hope to have the bunker open for practice next week.
What was the forward practice tee is now rough except for the portion next to the practice bunker which will become a teeing area to practice short shots. Jim Larkin has some great ideas planned for this area. This particular teeing area will be available for use in several weeks.
Hope to have the bunker open for practice next week.
What was the forward practice tee is now rough except for the portion next to the practice bunker which will become a teeing area to practice short shots. Jim Larkin has some great ideas planned for this area. This particular teeing area will be available for use in several weeks.
Monday, May 18, 2015
Weekly Schedule for May 18-24, 2015
Weather and unforeseen conditions can/will change the schedule.
-Sodding of lower driving range tee on Monday
-Installation of sand in practice fairway bunker at range
-Grooming of fairways
-Start mowing secondary roughs at 6 inches
-Sodding of lower driving range tee on Monday
-Installation of sand in practice fairway bunker at range
-Grooming of fairways
-Start mowing secondary roughs at 6 inches
Wednesday, May 13, 2015
Practice Fairway Bunker Construction
The staff has done an amazing job this week in constructing a practice fairway bunker in front of the driving range tee along the left side fence line. Shaping and drainage are complete. We will add sand and sod on Monday while the course is closed providing us easier access to this area without golfers on the range.
The turf on the entire lower tee will be removed and replaced with primary rough except for the portion directly behind the new practice bunker which will remain a tee and used to practice one's short game. Jim Larkin and staff have planned a great way to make the most of your short game practice in this area.
The following are pictures with short descriptions of the construction process to date:
The turf on the entire lower tee will be removed and replaced with primary rough except for the portion directly behind the new practice bunker which will remain a tee and used to practice one's short game. Jim Larkin and staff have planned a great way to make the most of your short game practice in this area.
The following are pictures with short descriptions of the construction process to date:
Concept drawn with turf marking paint. |
Removal of existing sod |
Initial shaping of the bunker shell |
Continued excavation of bunker shell |
Edging of bunker |
Drainage line excavation |
Gravel installation around drainage pipe in trenches |
Bunker outflow pipe |
Pinki supervising the work |
Monday, May 11, 2015
Weekly Schedule for May 11-17, 2015
Weather and unforeseen conditions can/will change the schedule.
-Construction of practice fairway bunker at range
-Continue adding sand to bunkers that need it. Also repair liner that is showing. Please remember sand will be soft in bunkers with new sand until we get some rains that will compact it.
-Verticut, topdress and fertilize greens on Monday
-Construction of practice fairway bunker at range
-Continue adding sand to bunkers that need it. Also repair liner that is showing. Please remember sand will be soft in bunkers with new sand until we get some rains that will compact it.
-Verticut, topdress and fertilize greens on Monday
Friday, May 8, 2015
Enkamat and Bunker Sand
Just in front of the tees on #1 where carts enter the fairway we installed material called Enkamat (Enkamat Website)
Under the matting is newly planted Turf Type Tall Fescue seed. The goal is for the turf to grow up through the porous Enkamat. Once fully grown the Enkamat will cover the crown portion of the plant near the soil surface protecting it from excessive wear. No guarantee it will work but it is worth a try.
Also, we have now added sand to 49 bunkers throughout the course using over 25 tons of sand. We will finish adding sand to the bunkers that need it next week.
Under the matting is newly planted Turf Type Tall Fescue seed. The goal is for the turf to grow up through the porous Enkamat. Once fully grown the Enkamat will cover the crown portion of the plant near the soil surface protecting it from excessive wear. No guarantee it will work but it is worth a try.
Also, we have now added sand to 49 bunkers throughout the course using over 25 tons of sand. We will finish adding sand to the bunkers that need it next week.
Wednesday, May 6, 2015
Additional Bunker Sand
This week we have added almost 23 tons of sand to 27 bunkers throughout the course. We have another 23 tons arriving Friday morning to continue adding sand to bunkers that need it.
Just a reminder, the fresh sand is soft and will not firm up until we get some rains. For now, enjoy the firm and fast conditions that the recent dry weather has allowed.
Just a reminder, the fresh sand is soft and will not firm up until we get some rains. For now, enjoy the firm and fast conditions that the recent dry weather has allowed.
Tuesday, May 5, 2015
Weekly Schedule for May 4-10, 2015
Weather and unforeseen conditions can/will change the schedule.
-Add sand to bunkers that need it
-Fine Fescue seeding in secondary roughs
-Rock wall repair at ruins on #12/#14
-Pre and post emergent herbicide application to primary rough
-Add sand to bunkers that need it
-Fine Fescue seeding in secondary roughs
-Rock wall repair at ruins on #12/#14
-Pre and post emergent herbicide application to primary rough
Subscribe to: