On Tuesday finish shaping was completed and the stacking of the Durabunker material began.


The most important part to successfully building a bunker with the Durabunker material is to have a compacted and level base as shown in the picture below. We were able to accomplish this using a plate compactor and laser level.




The above picture shows an example of a curve using the cut where triangles were removed from the pieces.


This picture shows an opposite curve to the bunker where pieces were cut with straight lines to achieve the needed angle.