Weather and unforeseen conditions can/will change the schedule.
-On Monday we will cross tine greens (not taking plugs) then topdress, apply soil amendments and water in
-On Friday we will remove the broken concrete located on the cart path from #2 to #3 (next to #11 Blue tee). Plywood will be placed for the weekend and concrete poured on Monday, April 28th there and where the cart path was cut on #3
-Continue removing bamboo to the left of hole #2 to our property line
-Mark and prep areas to be sodded
The bamboo work is incredibly difficult but necessary. How can you keep it from returning? Ron Pappas
ReplyDeleteOnce we have everything cut down we will apply a systemic herbicide multiple times to hopefully kill all the roots. This summer, as time allows, each plant will be dug out as much as possible. Then this Fall the area will be seeded to Fine Fescue.
Delete