After a month of no work due to poor weather conditions, Total Turf Golf Services is back to finish this work. Today they are finishing up the work to the right of #2 green next to the cart path.
Afterwards they will move to excavate out the sub-base for the Porous Pave path between #2 and #10.
While there are many moving parts, the schedule for now is the following:
-Finish prep for area between #2 and #10 on Thursday, March 19
-Sod area Tuesday, March 24 and Wednesday March 25
-Apply sub-base aggregate to cart path between #2 and #10 on Thursday, March 26
-Apply sub-base aggregate for walk paths on #3 and #7 on Friday, March 27
-Pour the Porous Pave material on Monday, March 30 and Tuesday March 31
Again, many factors involved including the weather that may alter this schedule.